Construction of the Sebzor HPP in the Roshtkala District Is in Full Swing
Read also
DUSHANBE, 15.06.2023 (NIAT Khovar) – The Minister of Energy and Water Resources Daler Juma got acquainted with the progress of construction work at the Sebzor HPP in the Roshtkala district.
Works at the substation 110/35/6 kV «Sebzor» were fully completed at the end of May this year. The specialists are working in the main building of the hydroelectric power plant, in the area of the dam, the building of the hydroelectric power plant and the main bridge.
At present, specialists are carrying out earthworks in the area of the dam and the water pipeline. The earthworks have been completed in the main building of the hydroelectric power station, and specialists have begun pouring concrete.
Also, at the end of April this year, work began on clearing the slopes along the road from the dam site to the hydroelectric power plant, and most of the work has been completed currently.
Responsible persons were given specific instructions regarding the quality of work and the acceleration of construction work.









Financing Issues Related to the Continued Construction of the Rogun HPP Discussed in Dushanbe
Implementation of Investment Projects and Attraction of Asian Development Bank Funds to Tajikistan’s Economy Discussed in Dushanbe
Tajikistan — Iran Expand Economic and Trade Cooperation
Tajik Delegation Participates in the Global India AI Impact Summit 2026
Tajikistan and Iran Discuss Direct Investment Opportunities in Tajik Economy
Tajikistan and Iran Discuss Prospects for Economic and Trade Cooperation
Tajikistan–Uzbekistan Commission Meeting Focuses on Expanding Economic Cooperation
Tajikistan, EBRD sign loan and grant agreements for energy loss reduction project
Tajikistan to Welcome Global Investors at “Dushanbe Invest-2025” Forum
Tajikistan’s Transport Minister Highlights Importance of Joint Projects in Seoul
Tajik–Swiss Business Forum Held in Dushanbe
Direct Air Connectivity Established Between Xi’an and Dushanbe