Construction of the Sebzor HPP in the Roshtkala District Is in Full Swing
Read also
DUSHANBE, 15.06.2023 (NIAT Khovar) – The Minister of Energy and Water Resources Daler Juma got acquainted with the progress of construction work at the Sebzor HPP in the Roshtkala district.
Works at the substation 110/35/6 kV «Sebzor» were fully completed at the end of May this year. The specialists are working in the main building of the hydroelectric power plant, in the area of the dam, the building of the hydroelectric power plant and the main bridge.
At present, specialists are carrying out earthworks in the area of the dam and the water pipeline. The earthworks have been completed in the main building of the hydroelectric power station, and specialists have begun pouring concrete.
Also, at the end of April this year, work began on clearing the slopes along the road from the dam site to the hydroelectric power plant, and most of the work has been completed currently.
Responsible persons were given specific instructions regarding the quality of work and the acceleration of construction work.









Tajikistan’s industrial sector creates 1,160 new jobs in first half of 2026
Trade and Economic Cooperation between Sughd and Batken Regions to Expand
Assets, liabilities and capital of financial credit institutions increase in Tajikistan
Tajikistan’s GDP reaches 81.7 billion somoni in first half of 2026
Inflation rate in Tajikistan reaches 2.4% in first half of 2026
Tajik IT diaspora’s role in advancing Tajikistan’s digital economy discussed in New York
Sanoatsodirotbonk Reports 1.3 Billion Somoni in Assets
Tajikistan’s foreign trade turnover exceeds $6.8 billion in first half of 2026
Tajikistan-Mongolia Business Forum held in Ulaanbaatar
Tajikistan, Mongolia Hold First Intergovernmental Commission Meeting on Trade and Economic Cooperation
Dushanbe to host fourth ECO Industry Ministers’ Meeting in September
Tajikistan exports more than $40 million worth of agricultural products in first half of 2026