Construction of the Sebzor HPP in the Roshtkala District Is in Full Swing
Read also
DUSHANBE, 15.06.2023 (NIAT Khovar) – The Minister of Energy and Water Resources Daler Juma got acquainted with the progress of construction work at the Sebzor HPP in the Roshtkala district.
Works at the substation 110/35/6 kV «Sebzor» were fully completed at the end of May this year. The specialists are working in the main building of the hydroelectric power plant, in the area of the dam, the building of the hydroelectric power plant and the main bridge.
At present, specialists are carrying out earthworks in the area of the dam and the water pipeline. The earthworks have been completed in the main building of the hydroelectric power station, and specialists have begun pouring concrete.
Also, at the end of April this year, work began on clearing the slopes along the road from the dam site to the hydroelectric power plant, and most of the work has been completed currently.
Responsible persons were given specific instructions regarding the quality of work and the acceleration of construction work.









Tajikistan, EBRD sign loan and grant agreements for energy loss reduction project
Tajikistan to Welcome Global Investors at “Dushanbe Invest-2025” Forum
Tajikistan’s Transport Minister Highlights Importance of Joint Projects in Seoul
Tajik–Swiss Business Forum Held in Dushanbe
Direct Air Connectivity Established Between Xi’an and Dushanbe
Tajik Delegation Participates in 69th IAEA General Conference
Swiss Cooperation Office Ready to Develop New Initiatives in Tajikistan
Tajikistan attracts USD213 million from international financial organizations
Tajikistan Chamber of Commerce and Industry Opens Representative Office in Beijing
International Artificial Intelligence Conference to Be Held in Dushanbe in October
Tajikistan’s Foreign Trade Turnover Exceeds $4.7 Billion in First Half of 2025
Chinese Investors Familiarize Themselves with Activities of Kulob Free Economic Zone